Cedar Ridge campus update: July 27

After long deliberations and multiple meetings with our project manager and general contractor, Skyward Construction, it is clear Skyward will not be able to complete the Cedar Ridge (Pioneer campus) renovation project by the original agreed upon deadline. However, we want our community to know that we are pleased with the efforts of our local sub-contractors, as they have been diligent in getting their work done to prepare the site for staff and students.

Our start date at the new Cedar Ridge campus will now be November 27, after Thanksgiving break. In the meantime, students will begin their year on September 5 at the current Cedar Ridge campus. We will prepare the current campus for students, as we do each year, and will continue to update our community as we progress with the new Cedar Ridge campus project.

While we had hoped to start the year in our new school, we will do everything in our power to accommodate a smooth transition. We are still excited about moving into the newly renovated campus and the promise it holds for our students and staff.